A11 Spooner Row to Thickthorn Concrete Reconstruction and Surface Repairs Scheme

Summary (See full document from National Highways in this link)

Work on the A11 between Spooner Row and Thickthorn during the coming months:

• Phase 1 – A11 Tuttles Interchange to Thickthorn Interchange road surface repairs

• Phase 2 – A11 Spooner Row to Tuttles Interchange reconstruction

Phase 1 – Road Surface repairs

From mid-October – every evening from Sunday at 8pm to 6am Friday morning. Closure of the A11 between Tuttles to Thickthorn, finishing in winter.

Also some weekend closures to work on larger repairs.

Signed diversion routes will be in place

Phase 2 – Preparation

From 15 September 2021 for seven weeks – Single lane closure between 9am and 4pm on the A11 between Spooner Row and the Tuttles Interchange on either carriageway depending on the work requirement.

Also work overnight from 8pm to 6am.

In November and December several mid-week night-time slip road closures, with number of weekend night-time carriageway closures.

Phase 2 – Reconstruction

Will commence in early 2022 for the A11 road between Spooner Row and the Tuttles Interchange.